Rehabilitation of al Zarqa Triangle Irrigation Project. The works included:
- Replacement of the existing Asbestos pipe with UPVC pipes, 28 km length
- Rehabilitation of the existing filters of the sedimentation basins
- Rehabilitation of the existing service road 4.4 km length and the culverts
- Rehabilitation of existing pump station
- Replacement and maintenance of aerators of the main conveyor pipeline with 900 mm diameter and 800 mm diameter
Installation of new pumps for irrigation basin (25)