Additional classrooms and WC units to existing schools at Irbid Governorate, whereas the project was phased over three groups:
- Group (A): included 6 schools with 3,865 m2 total extensions’ built up area
- Group (B): included 4 schools with 2,952 m2 total extensions’ built up area
Group (C): included one school extension with 775 m2 built up area