Rehabilitation of North runway and taxiway at Queen Alia International Airport (QAIA) including pavement milling, installation of lights, installation of new equipment, etc., replacement of some elements and installation of new ones where necessary in addition to the supervision of the general safety works at the project site. Project works included:
Civil Works:
- Removal of the asphalt surface layer of the runway and the restoration of asphalt works according to international airports specifications
Electrical Works:
- Removing & inspecting the existing halogen lighting units at the runway, verifying functionality and reusing the working ones.
- Inspecting and verification of electrical cables status, replacing malfunctioning and re-using the functioning cables.
- Supply and installation of LED lights where needed within the project site.
- Supply and installation of electrical and communications equipment used in the runway.
Health and Safety Monitoring