The project comprised of two main components.
- Irbid refugee camp’s infrastructure which included
- Roads construction of 10,700 m2
- Paving existing roads of 4,750 m2
- Concrete corridors of 23,000 m2
- Sidewalks of 8,100 m2
- Storm water drainage network of 470 m2
- Maintenance and development of electrical and lighting networks.
- Storm water drainage system outside the camp’s boundaries, including:
- Storm water drainage network of 2,300 m length and 1,200 mm diameter pipes, 46 manholes
- Box culverts of 550 m length
Reconstruction of roads and pavement of 5200 m
2